Fire NOC in Andhra Pradesh, from drawings to certificate.
How the fire NOC works in Andhra Pradesh: height triggers, where to apply, the provisional and occupancy NOC, drawings to prepare, with a pre-check for your drawings.
What to know first about the Andhra Pradesh fire NOC
Fire services in Andhra Pradesh are handled by the Andhra Pradesh State Disaster Response and Fire Services Department, under the Andhra Pradesh Fire Service Act 1999 and its rules. Thresholds, fees and portals change, and several published guides disagree, so each point below is marked as reported where it comes from a secondary source.
- Reported: the trigger under the 1999 Act as amended in 2006 is height above 15 metres for commercial or business use and 18 metres and above for residential use. A separate AP Building Rules amendment refers to a 24 metre figure, so confirm which applies to your building type.
- Reported: a digital fire NOC portal allows provisional, occupancy and renewal NOCs to be applied for online, with certificates generated automatically.
- Reported: applications for taller buildings are handled at the Director General level and smaller buildings at district level.
- Reported: some fees are quoted per square metre of built-up area. Confirm against the current official fee schedule.
Where to apply
- Andhra Pradesh fire services online NOC portal (the address has changed; confirm the live one on an AP government page).
- Industrial projects may also route fire approvals through the Single Desk Portal under the Department of Industries.
Which code edition applies
India replaced NBC 2016 with NBCS 2026 (SP 7:2026) on 30 April 2026, and the fire provisions moved from Part 4 to Part F as guidance for states. What is mandatory in your project depends on what the state has adopted. Read NBC 2026 explained, and write the edition you designed to on every drawing.
Drawings and documents to prepare
- Key site plan with surrounding roads, fire tender driveway and gates.
- Floor plans with exits, staircases, walking paths, refuge areas and fire lifts marked.
- Fire-fighting layout: wet risers, hydrants, sprinklers, manual call points, detectors.
- Pump room and water storage schedule.
- Occupant load and egress calculations.
- For the final certificate: installation and testing certificates for the fire systems.
Get the one-page version: the fire NOC pre-submission checklist.
Common reasons applications are sent back
- Exit widths that do not match the calculated occupant load.
- Travel distance measured in a straight line rather than along the walking path.
- Missing staircases, refuge areas or fire lifts where the building height requires them.
- Fire tender access that is too narrow or has tight turns.
- Drawings that are inconsistent between sheets.
Frequently asked questions
Who issues the fire NOC in Andhra Pradesh?
the Andhra Pradesh State Disaster Response and Fire Services Department, under the Andhra Pradesh Fire Service Act 1999 and its rules. Confirm the current process on the official portal before you file.
Do I need both a provisional and a final fire NOC?
Most states issue a provisional certificate at plan stage and a final one after the fire systems are installed and tested, and the final one is typically needed before occupation. Confirm the exact certificates your project needs with the authority.
Can Verify AI pre-check drawings for this state?
Yes. Verify AI checks IFC, DXF and PDF drawings against NBC and NBCS 2026 requirements and records the edition and clause in each finding. It is a pre-check, not an approval.