What to know first about the Karnataka fire NOC
Fire services in Karnataka are handled by Karnataka State Fire and Emergency Services (KSFES), under the Karnataka Fire and Emergency Services Act. Thresholds, fees and portals change, and several published guides disagree, so each point below is marked as reported where it comes from a secondary source.
- Reported: a notification made an NOC from KSFES mandatory for structures standing over 21 metres, with the Act amended accordingly. Confirm the current height trigger.
- Reported: buildings at 21 metres and above are routed to the head office, where the Director General signs off.
- Local building plan approval goes through the municipal body (for example BBMP in Bengaluru), and the fire clearance is a separate step.
Where to apply
- KSFES online services (register as a public user and apply for the NOC or clearance). Sources list different domains for the portal, so confirm the live address on a Karnataka government page.
Which code edition applies
India replaced NBC 2016 with NBCS 2026 (SP 7:2026) on 30 April 2026, and the fire provisions moved from Part 4 to Part F as guidance for states. What is mandatory in your project depends on what the state has adopted. Read NBC 2026 explained, and write the edition you designed to on every drawing.
Drawings and documents to prepare
- Key site plan with surrounding roads, fire tender driveway and gates.
- Floor plans with exits, staircases, walking paths, refuge areas and fire lifts marked.
- Fire-fighting layout: wet risers, hydrants, sprinklers, manual call points, detectors.
- Pump room and water storage schedule.
- Occupant load and egress calculations.
- For the final certificate: installation and testing certificates for the fire systems.
Get the one-page version: the fire NOC pre-submission checklist.
Common reasons applications are sent back
- Exit widths that do not match the calculated occupant load.
- Travel distance measured in a straight line rather than along the walking path.
- Missing staircases, refuge areas or fire lifts where the building height requires them.
- Fire tender access that is too narrow or has tight turns.
- Drawings that are inconsistent between sheets.
Frequently asked questions
Who issues the fire NOC in Karnataka?
Karnataka State Fire and Emergency Services (KSFES), under the Karnataka Fire and Emergency Services Act. Confirm the current process on the official portal before you file.
Do I need both a provisional and a final fire NOC?
Most states issue a provisional certificate at plan stage and a final one after the fire systems are installed and tested, and the final one is typically needed before occupation. Confirm the exact certificates your project needs with the authority.
Can Verify AI pre-check drawings for this state?
Yes. Verify AI checks IFC, DXF and PDF drawings against NBC and NBCS 2026 requirements and records the edition and clause in each finding. It is a pre-check, not an approval.
Related
- Verify AI for India
- How to apply for a fire NOC online
- Fire NOC pre-submission checklist
- Do I need a fire NOC? (tool)